Logistics Facility for Ajman Free Zone Authority at the New Industrial Complex at Al Jurf
Client
Ajman Free Zone Authority
Consultant
Cansult Engineer & Project Managers
Location
Ajman, United Arab Emirates
Built-Up Area
95,098 square meters
Completion Date
December 2007
Scope of Work
Turnkey
The 95,000 square meter facility consists of 15 warehouses constructed on 200,000 square meters of land requiring over 2,300 tons of steel and 12 months to complete. Amana modified the original design to allow for increased operational flexibility and to maximize the free space availability in the storage facilities. The first warehouse was delivered 210 days from start with an additional warehouse completed every 10 days thereafter.