Client: Oman Air
Consultant: SEMAC & Partners LLC
Location: Muscat
Completion Date: February 2010
Duration: 6 months
Built-up Area: 5,700sqm
Scope: Turnkey

Due to the need for Oman Air to have expand its offices and hire staff within 6 months, Amana was contracted on a fast-track basis to built a new office building at the airline’s headquarters in Seeb, Muscat.

The building is designed as a steel structure with the necessary external, internal finishes and partitions as per Oman Air’s needs for their office expansion requirements.

The project required over 300 tons of steel and was completed in 180 days.